Durham Solar Farm

Project Owner: Heelstone Energy
Contact: Richard Wright

Project overview:

  • 3.5 MW AC fixed-tilt ground mounted system over 22 acres
  • Produces enough clean energy to power approximately 700 homes
  • Construction took approximately 6 months

Services provided:

  • Drew construction drawings:
    • Construction drawings detailed access, drainage and soil and erosion control
    • Provided 5 full sediment basin designs as part of the sites erosion control package
    • Drawings identified temporary construction and permanent driveway entrances
    • Stormwater Management plan designed to meet Durham County Stormwater Ordinance – stormwater wetland and two permanent dry detention ponds required
  • Obtained approvals & conducted permitting:
    • Site plan – Durham city/county planning
    • Land Disturbance Permits – Durham County
    • Driveway permit – NCDOT
    • Stormwater Permit – Durham County
  • Provided construction administration:
    • Performed periodic field visits during construction to ensure compliance with the approved plans
    • Drew stormwater wetland/dry detention pond as-built drawing