Stout Solar Farm
Project Owner: Strata Solar
Contact: Brent Niemann, P.E. (919) 960-6015
Project overview:
- 6.6 MW AC fixed-tilt ground mounted system over 42 acres
- Produces enough clean energy to power approximately 766 homes
- Has an operating life span of over 30 years
- Construction took approximately 14 weeks
- Constructed by a crew of 80 local contractors
Services provided:
- Created construction drawings:
- Prepared construction drawings detailing access, drainage and soil and erosion control
- 4 sediment basins provided for erosion control
- Temporary construction and permanent driveway entrances
- Stormwater Management plan designed to meet Orange County Stormwater Ordinance – innovative stormwater swale used to meet requirement
- Conducted permitting:
- Land Disturbance Permits – Orange County
- Driveway permit – NCDOT
- Stormwater Permit – Orange County
- Provided construction administration:
- Conducted periodic field visits during construction to ensure compliance with the approved plans
- Stormwater swale as-built drawing