Warsaw Solar Farm
2nd largest solar farm in NC when completed!
Project Owner: Duke Energy
Contact: Brent Niemann, P.E., Strata Solar
Project overview:
- When completed it was the second largest of solar farm in North Carolina
- 65 MW AC fixed-tilt ground mounted system with approximately 850,000 solar panels on ±550 acres
- Produces enough clean energy to power approximately 13,000 homes annually
- Construction took approximately 9 months
Services provided:
- Created construction drawings:
- Prepared detailed construction drawings detailing access, drainage and soil erosion control
- Prepared a phase 1 Construction Drawing package to expedite the construction of the substation
- 7 different temporary construction and permanent driveway entrances
- Jurisdictional impact designs for 4 stream crossings, 8 tributary crossings and 2 wetland crossings
- Conducted permitting:
- 2 separate Land Disturbance Permits (phased), NC DEMLR, Environmental Quality
- 7 driveway permits (5 different land owners), NCDOT
- 2 Encroachment Permits for underground utility crossings